One year of heat from Reichenhall for Bad Reichenhall
23.01.2023
One year of heat from Reichenhall for Bad Reichenhall
This concept was awarded the first tender for iKWK systems by the Federal Network Agency in Berchtesgadener Land in 2018 - as one of only five projects.
As a result, Stadtwerke Bad Reichenhall awarded the contract for the general technical planning to Gammel Engineering to build the new energy center and the district heating network.
During the concrete planning phase, a power plant was created consisting of
two natural gas CHP units, each with 3.4 megawatts of electrical (MWel) and 3.2 MW of thermal (MWth) output,
two ammonia groundwater heat pumps with 1.5 MWth and
two power-to-heat plants of 1.2 MWth each. This also includes
three heat storage units of 250 m³ each and one
peak load boiler with a heat output of 5 MW.
The heating network was developed in the first expansion stage with a route length of around 6 km, slightly less than expected in the feasibility study
The entire power plant was integrated into the existing Stadtwerke underground bus garage - which of course requires meticulous as-built surveys and 3D planning.
Yoga has been an integral part of our company routine for exactly one year now! Every Tuesday after work, around 8 to 12 employees meet for a yoga session with Susanne Ohneis. What originally began as a test phase has now become a fixed part of our health program - and many colleagues can no longer imagine their weekly schedule without it.
Autumn is duck season - our joint duck dinner 2025
At this year's duck dinner at Landgasthof Röhrl in Pullach, we were once again treated to a delicious meal - crispy duck, served with red cabbage and dumplings.
CONNECTA in Regensburg is the largest company contact fair in Bavaria and has established itself as an important meeting point between business, social institutions and students. Every year, numerous companies looking for motivated young talent present themselves there - and we were proud to be one of them!