One year of heat from Reichenhall for Bad Reichenhall
23.01.2023
One year of heat from Reichenhall for Bad Reichenhall
This concept was awarded the first tender for iKWK systems by the Federal Network Agency in Berchtesgadener Land in 2018 - as one of only five projects.
As a result, Stadtwerke Bad Reichenhall awarded the contract for the general technical planning to Gammel Engineering to build the new energy center and the district heating network.
During the concrete planning phase, a power plant was created consisting of
two natural gas CHP units, each with 3.4 megawatts of electrical (MWel) and 3.2 MW of thermal (MWth) output,
two ammonia groundwater heat pumps with 1.5 MWth and
two power-to-heat plants of 1.2 MWth each. This also includes
three heat storage units of 250 m³ each and one
peak load boiler with a heat output of 5 MW.
The heating network was developed in the first expansion stage with a route length of around 6 km, slightly less than expected in the feasibility study
The entire power plant was integrated into the existing Stadtwerke underground bus garage - which of course requires meticulous as-built surveys and 3D planning.
20 Years at Gammel Engineering—Congratulations, Florian!
Today we celebrated a special anniversary: Florian Prantl has been with Gammel Engineering for 20 years. Over these two decades, technologies have changed, projects have evolved, and teams have been reorganized.
One thing has remained constant: Florian Prantl is a reliable member of the Gammel Engineering team.
In 2026, Gammel Engineering was once again ready to head to the Gillamoos! Together with our partners, we kicked off the “fifth season” in Abensberg on Friday, as is our tradition.
Michael and Gudrun Gammel rounded out the kickoff of the new yoga season with a light meal. With a particularly delicious meal featuring fish and cheese, we were able to wind down the evening in a cozy atmosphere.