New recoolers for the data center at AUDI !

13.06.2017

New recoolers for the data center at AUDI !

On Thursday, 25.05.2017, a 400-ton crane with a 60m boom was erected. On Friday, the old recoolers were then dismantled and the new ones put back in place.

From Monday, 29.05.2017, the piping and electrical integration of the recoolers took place.Many thanks to everyone involved for the smooth process.