Press

Factory set up for the future

01.02.2017

Factory set up for the future

Gammel Engineering was commissioned with the planning of the technical building equipment for this project.

Read the report here in the

IHK Wirtschaft Konkret 02/2017

More News

Press

Groundbreaking ceremony for the inclusive Franziskus children's home in Abensberg

Read more
14.10.2025
Press

HLH reports: Digital precision meets sustainability - Atlas Copco's ECC as a lighthouse project

Read more
10.10.2025
Press

Kelheim sets an example - sustainable district heating from a strong partnership

Read more
06.10.2025
Experience and innovation
in every project. *
Contact
Gammel Engineering GmbH
An den Sandwellen 114
93326 Abensberg
Office Cham
Gewerbepark Chammünster Nord 3
93413 Cham

Careers at Gammel Engineering